Archival view of Venezuela's Planta Centro thermal power station, where a Chinese company plans to restore 600 MW of generation

China Moves to Restart 600 MW at Venezuela’s Planta Centro Power Plant

Writer: Carlitos Marquez
Carlitos Marquez
1 hour ago
3 min read

CARABOBO, VENEZUELA — China Machinery Engineering Corp. is preparing to restart a 600-megawatt generating unit at Venezuela’s Planta Centro thermal power station, offering the prospect of additional electricity for a country still struggling with persistent outages. The targeted start is in November, but the unit is not yet confirmed to be supplying power.

Bloomberg Línea reported on October 24, citing people familiar with the project, that the Chinese company is working to reactivate Unit 6 at the complex, about 135 kilometers west of Caracas. The generator is designed to use fuel oil supplied by Venezuela’s state oil company, PDVSA. The wider station has operated far below its former capacity for years.

The effort follows a cooperation agreement dating to the government of Hugo Chávez. Rather than construct a new station from scratch, the work seeks to return existing Venezuelan generating infrastructure to productive use. A successful restart would make Chinese engineering an immediate part of the country's power-recovery effort.

Archival photograph of Venezuela's Planta Centro thermal power station in Carabobo, photographed in 2010

Planta Centro in Carabobo, Venezuela. Archival photograph taken April 22, 2010, not an image of the current repairs. Photo: ArwinJ / Wikimedia Commons, CC BY-SA 4.0.

A major unit in a weakened grid

Planta Centro’s six-unit complex once had installed capacity exceeding 2,500 megawatts. Bringing back a single 600-megawatt machine would therefore recover a substantial share of its historic output on paper. The real test is whether the generator can operate reliably, obtain enough fuel, and deliver electricity through a strained transmission and distribution system.

Years of equipment failures, insufficient maintenance and investment, and the effects of international sanctions have complicated Venezuela’s efforts to stabilize its electricity supply. Bloomberg Línea also reported widespread complaints about service interruptions and cited the Venezuelan Observatory of Social Conflict’s tally of 531 electricity-related protests in September. For households and businesses, the question is how much dependable power will actually reach them.

China’s role and the November deadline

Venezuelan authorities described Chinese cooperation as part of their electricity-recovery program earlier this month. In an October 8 announcement, the government said Unit 6 was expected to connect to the grid soon and outlined a wider objective of restoring roughly 1,300 megawatts of generation before the end of 2026.

But the engineering challenges remain. On October 19, Venezuelan outlet El Pitazo quoted electrical engineer José Aguilar warning that problems involving the unit’s bearings and shaft supports could delay its return. Bloomberg’s reported November target therefore remains a timetable, not proof of a completed restart. CMEC and Venezuelan authorities had not publicly supplied the reporters with a firm operational date.

Electricity and economic sovereignty

The project also reflects the strategic importance of Chinese-Venezuelan economic ties. As Washington seeks to curb Beijing’s influence in the region, the planned repair puts an essential public service at the center of that competition. Other foreign companies have also been involved in Venezuelan electricity projects, including efforts associated with GE Vernova and Argentina’s Impsa.

A fully operating Unit 6 would not solve every problem facing Venezuela’s grid. It could nevertheless restore meaningful capacity at one of the country’s largest thermal power complexes. What matters now is whether the work advances from announced megawatts to sustained, measurable electricity generation.